On April 8, at the meeting with the People's Committee of Dong Nai Province, Prime Minister Nguyen Xuan Phuc directed to speed up the handover of ground for Long Thanh airport construction.
Long Thanh Airport with a construction area of 5,000ha, Dong Nai People's Committee said that the province focused on clearing 1,810ha to soon allocate land to the Airport Authority in 2020 to build Long Thanh airport phase 1 .
Up to now, Dong Nai People's Committee has completed tally of 1,145 households and individuals with an area of 630ha; the remaining is Dong Nai Rubber Corporation's land, which has been issued a decision on land acquisition by the Provincial People's Committee and approved compensation and support options.
The remaining area (3,190ha), for the land of Dong Nai Rubber, the province has paid compensation and support; This unit has handed over the clean ground. At the same time, the province is hiring a consultancy unit to determine specific land prices for compensation, approve compensation plans and pay for households completed in the second quarter of 2020.
Regarding the situation of frequent traffic jams on Highway 51 connecting Dong Nai - Ba Ria Vung Tau. Previously, on February 7, the Prime Minister agreed in writing to assign the People's Committee of Ba Ria - Vung Tau province to prepare a pre-feasibility study report for the Bien Hoa - Vung Tau Expressway Project, parallel directions for to the West and about 1-2km to Highway 51.
In order to promote the effectiveness of the Long Thanh airport project, the National Assembly agreed to add two more land roads to the airport. Dong Nai People's Committee proposed to the Prime Minister to soon approve the feasibility study report of Long Thanh airport to have a basis for deploying land acquisition of these two connecting routes.
At the same time, he proposed to the Prime Minister to direct the Vietnam Airport Corporation to invest in building in front of Route 1 to build public roads, serve airport construction; propose to the Prime Minister, the Ministry of Transport to study to expand the Ho Chi Minh City - Long Thanh - Dau Giay expressway to 8-10 lanes, ensuring the satisfaction of the demand for connecting Long Thanh airport with Ho Chi Minh City; speeding up the construction of Ring Road 3, Tan Van - Nhon Trach section, this route will combine with route 25B of Nhon Trach new urban area to connect to national highway 51.
Assessing the clearance of Long Thanh airport, Prime Minister Nguyen Xuan Phuc said that the ground clearance progress is still slow, Dong Nai province is proposed to focus on this work, the goal is to try to disburse capital. over VND 17,000 billion this year. At the same time, the ministries and branches are requested to embark on supporting Dong Nai to accelerate the progress, disburse all the capital, ensure the standards and quality of the project, and mobilize and support in accordance with regulations. of the law for people to support and hand over the ground for construction